Carbon Bake Furnace 1 and 2 Replacement Studies, Queensland, Australia

Haga clic aquí para la versión en español

Boyne Smelters Limited commissioned the SN C-Lavalin/SKM Joint Venture for the preparation of a pre-feasibility and feasibility study, aimed at examining various options for the replacement of the existing Anode Baking Furnaces 1 and 2 located at Gladstone, Queensland.

The PFS assessed the following key issues:

  • Technical advantages and disadvantages
  • Capital and operating costs to an accuracy of +/- 20%
  • Project implementation schedule and constraints
  • Risk profile
  • Sustainability analysis
  • Feasibility study execution plan.
Resulting from the assessment of key merits/issues of each option, the recommendation for a “go forward” option to be taken into the Feasibility study phase was replacing the existing furnaces using new “open” technology in a new building constructed to the north of the existing anode baking furnace 3.

 

This option includes the following facilities:

  • “Open” Technology for the furnace operation
  • Furnace Tending Assembly
  • Anode handling systems to tie into the existing operation
  • Fume treatment centre for treatment of emissions
  • Building (280m long x 36m wide x 24m high).
The EPCM execution phase is currently underway with a first baked anode aimed at October 2010.

For further information, contact: Sinclair Knight Merz