Mandurah Regional Water Scheme Telemetry

 Project Highlight - Mandurah Regional Water Scheme 

Sinclair Knight Merz was commissioned to undertake the production of a Preliminary Design Report for the Mandurah Regional Water Scheme SCADA. Mandurah is a rapidly expanding city about an hour’s drive south of Perth, which experiences significant influxes of tourists on weekends and holidays.

The work included surveys of the 31 proposed telemetry sites, review of the proposed communication links, preparation of a conceptual functional specification and a design report, including a detailed budget estimate.

The Mandurah Telemetry System project was the first that used the standardised design criteria set out in the client’s Telemetry Design Manual DE-6 (developed by Sinclair Knight Merz under another commission) and the four year periodic supply contract for telemetry systems with ABB.

Sinclair Knight Merz also assisted the client in preparing its internal Project Management Plan for this project.

Program for Delivery:

12 months

System Vendor:

ABB Transmission Pty Ltd

Project Budget:

AU$1.3 million

The involvement of Sinclair Knight Merz in the Mandurah Telemetry Systems Project brings the following benefits to your project:

  • expertise in SCADA and Telemetry 
  • experience in the conduct of extensive surveys 
  • demonstrated capacity to deliver results.
For further information, contact: Sinclair Knight Merz