Power Supply to Premier Mine, WA

 Project Highlight - Power Supply to Premier Mine,

Sinclair Knight Merz was commissioned by Western Collieries to design the power supply to Premier Mine with the following design criteria:

  • ultimate electrical excavator fleet for substation design purposes of two P&H electric shovels
  • a maximum demand of 7500 kW in five years
  • mine distribution voltage of 22 kV.

The following considerations in the design of the power supply included:

  • availablity of the power supply versus the consequence of power outage
  • a high fault level was required to limit voltage fluctuation caused by excavator swinging loads
  • the equipment had to be rated for the electrical impact loading caused by excavators, where the momentary load on equipment can substantially exceed equipment nameplate rating
  • harmonic distortion due to static motion drives on excavators.

The main features of the proposed supply to the mine were:

  • a 132 kV substation established adjacent to the mine infrastructure. The substation was separated into two sections; one operated and maintained by Western Power and the other by WCL
  • the Muja-Worsley 132 kV transmission line routed into and out of the Western Power switchyard
  • two 132/22 kV 10/13 MVA transformers, each capable of supplying the total mine load
  • a 22kV indoor switchboard to distribute power to the mine. The existing WCL load was also to be transferred to this system.
For further information, contact: Sinclair Knight Merz